CALL US NOW | 06-857 8303

Pourerere Beach

After the severe weather event along the Hawkes Bay Coast line in 2011 Barker Contractors were commissioned by Opus Consultants and the local residents committee to repair the damage behind a number of beach cottages, along with moving some 4,000 cu.m of hill side placing an open water channel for future control.

The repairs to the local cottages involved removing all spoil that came down from the hills, demolition and removal of 2 damaged houses, and building a retaining wall structure the entire length of the Southern section of beach behind the houses. This called for some interesting techniques, but the result was exactly to what the engineers called for.

The removal of the hill was a project that required careful planning as the area was steep hill country and the soil had to be removed and used as fill to repair some of the slip damaged on the farm.

Striping topsoil was done by bulldozer, zero swing excavators and tracked dump trucks then took soil away, diggers cut and form batters, using a 5 ton machine to form the 700m of drainage network, and finally a liner was placed along entire drainage system flowing onto a gabion drainage disbursement field. Coconut matting was used to retain the grass-seed sown and trees planted to finish the project.
{{errors.first('rs-ce93-4d2e-a568', 'rs-ce93-f2fc-1d56')}}
{{errors.first('rs-ce93-4d2e-dde5', 'rs-ce93-f2fc-1d56')}}
{{errors.first('rs-ce93-4d2e-03e0', 'rs-ce93-f2fc-1d56')}}

Message Sent

QRS - Quality Roading Services (Wairoa) Ltd

For over 20 years Barkers have had an association with QRS – Quality Roading Services (Wairoa) Ltd - first formed with working on bridge maintenance contract held by QRS in CHB. This relationship grew into a resource sharing, project sharing relationship.

Michael - himself worked on the Marys Hill, Willowflat flood damage contract for Wairoa District Council, held by QRS. Barker's contract was providing the ground works for some of the larger Gabion walls built in the Wairoa area. 18 drop outs in total. One site consisted of 300 Gabion baskets. Barkers also provided the Gabion rock for this project.

A dropout on a section of road on State Highway 2, just north of Raupunga proved to be very challenging with many thousands of cubic metres of spoil to be removed and replaced with hard fill. This required the use of Barkers tracked dump trucks and excavators along with help from another Wairoa contractor.

Dam Construction

In 2015 the company was asked to rebuild a large dam just before winter. It was a demanding job, and again timing was gauged against winter. The wall was stripped out, all loose mud and debris removed, then construction began. Using our Motor-scraper, 2 bulldozers, Excavators and a 18t sheeps foot roller our team completed this in time for the winter rains.

Horse Arenas



Barkers have built a number of horse arenas. One of the larger arenas to be constructed also included all site work for a stable complex. These clients were particular on what they required. We understood the project brief and they, the clients, were very understanding of the project build and a pleasure to work with.
80m x60m with all-weather drainage system, along with the Stable complex and full landscaping was the scope.

This arena is used as a training ground, equestrian schooling, and also used by overseas riders when staying in Hawkes Bay.

Mr Apple

Re-Metalling and Resurfacing the Orchards roading network – Central Hawkes Bay

SAE on behalf of Ministry of Education

Barker Contractors over the years have been involved in many cabling and duct laying jobs. Working principally as a sub-contractor to SAE Napier, we have installed many ducts in schools for Back Boning of voice and data. We have worked in Auckland, Gisborne, Manawatu, Wanganui and Hawkes Bay schools. This work often involves very careful isolating of services and hazards, trenching though concrete, pavers, bitumen and grass, laying of multiple ducts, installing cable pits and all fully reinstating all surfaces.

Centralines

Since Barker Contractors have been in business, Centralines, formally CHB Electric Power Board have been a client. 35 years of relationship. The first job was Michael working with his Trac-Grip backhoe at the substation near what's is now Takapau Meat Works. With the purchase of a Ditchwitch 4010 Michael went on to trenching at a new subdivision at Porangahau beach. From there, the company has trenched in kilometres of cable and duct into many streets in and around Waipukurau, Waipawa.
One of the more involved projects undertaken was the Central Business area of Waipukurau. 1.7km of duct and cable laid. Once completed, Barkers then laid the main street under the shop verandas, often working a night shift so not to disturb the retailers.

Undergrounding of the Main Street of Waipawa – SH2 was another challenge. Again, along under the shop verandas, all street lights moved.

Barkers compete on the open market for this work.

CHB District Council

Over the years Barkers have worked with the CHB District Council. The Russell park development saw Barkers lay 700m of new footpath and vehicle crossings installed into the park.
Just recently Barkers completed the site works for the new Porangahau Water reservoir up grade. This was enlarging the area, retaining walls constructed, site drainage, curb and channels poured and resealing a section of road.

Water mains, sewer, waste water reticulation has all been undertaken by Barkers, again for over 35 years.

Open tender market for much of this work.

Quarry Supplies

Last roading season Russell Roads Ltd was successful in winning a number of AWPT's from the CHB District Council. Barker's were then successful in providing all the crushed aggregate needed for these Area Wides. Approx. 25,000 cubic metres of Transit Spec 40mm and 65mm were supplied to them.

Currently Downers are drawing on our 2 quarries for product used in CHB.
Alongside this, Barkers own requirements for forestry roading, plumbing companies looking for drainage stone, and private sales kept the quarries very busy over the summer months.

Barkers were operating 3 sites, and just recently sold two of these to another local contractor alowing a close working relationship. Having these quarries had allowed Barkers to forever expand their product range, which now includes not only roading aggregate, but moving towards garden chip and limestone rock.

All sites are operated by qualified Quarry managers and are Work Safe approved.

DOC

One of Barkers smallest machines being flown by Lake View Helicopters on way to a DOC track to start a project with HEB Construction.
 

This product has been added to your cart

CHECKOUT